13 Portsmouth Water Plc
|
Overall water quality supplied by Portsmouth Water Plc in 2003 |
- 23,369 tests were carried out on samples taken by Portsmouth Water Plc in 2003.
- 99.9% of these tests complied with the Regulations.
|
|
Company Information |
Amount of Water Supplied: |
187.45 Ml/d |
|
Consumers Supplied: |
655,382 |
|
Areas of Supply: |
Hampshire, West Sussex and |
| |
Portsmouth |
|
Water Composition: |
10% from rivers and reservoirs |
| |
90% from wells, boreholes and |
| |
aquifers |
|
Treatment Works: |
20 |
|
Service Reservoirs: |
41 |
|
Km of Mains: |
3,247.34 km |
|
Water Supply Zones: |
23 |
|
|
Water quality at treatment works, in service reservoirs and in water supply zones
To be wholesome, water must comply with the water quality standards for the parameters set out in the
Water Supply (Water Quality) Regulations 1989. In 2003, the Company carried out a total of 23,369 tests
on samples of water leaving its 41 water treatment works, from its 20 service reservoirs and from
consumers’ taps in its 23 water supply zones. Of these, 99.9% (23,346) complied with the standards set
down in the Regulations. However, 0.1% (23) tests did not meet the standards. A list of the parameters, the
relevant standards and their significance can be found at the beginning of this section.
Water quality leaving treatment works
A comparison of the Company’s performance in 2003 with data for 2002 and 2001, is given below. There
has been a significant decrease since 2001 in the number of tests carried out on samples from treatment
works, in which total coliforms were detected. All other differences were not considered significant.
During 2003, failures of the total coliform standard at two works were considered trivial, and unlikely to recur.
Two failures of the faecal coliform standard occurred at two works. These were regarded as trivial or
unlikely to recur.
In 2003, 1,306 regulatory samples for Cryptosporidium were taken at five sites. Very low numbers of
oocysts were detected in 69 samples from three sites. All results were well below the treatment standard
and there were no reported outbreaks of cryptosporidiosis.
Water quality in service reservoirs
A comparison of the Company’s performance in 2003 with data for 2002 and 2001, is given below. There
has been a significant decrease since 2001 in the number of service reservoirs in which total coliforms were
detected. All other differences were not considered significant.
During 2003, total coliforms were occasionally detected at two service reservoirs. However, there were no
failures of the total coliform standard at any service reservoir.
The failure of the faecal coliform standard at one service reservoir was considered trivial or unlikely to recur.
Water quality in water supply zones
The table below shows the data for the key parameters and any other parameters where there was a failure
of the standard. All other parameters were fully compliant. A comparison is also given for parameters failing
the standards in 2002 and 2001.
|
Parameter
|
Total
number
of tests
|
Tests not meeting
standard
|
Number of
failures
covered by
Undertakings
|
Number of zones not
complying with the standards
(number of zones in
2003 = 23)*
|
|
|
|
No
|
%
|
|
2003
|
2002
|
2001
|
|
Coliforms
|
1,762
|
2
|
0.11
|
0
|
0
|
0
|
0
|
Faecal coliforms
|
1,762
|
0
|
0.00
|
0
|
0
|
1
|
0
|
Colour
|
143
|
0
|
0.00
|
0
|
0
|
0
|
0
|
Turbidity
|
154
|
0
|
0.00
|
0
|
0
|
0
|
0
|
Odour
|
160
|
0
|
0.00
|
0
|
0
|
0
|
0
|
Taste
|
160
|
0
|
0.00
|
0
|
0
|
0
|
0
|
Hydrogen ion
|
123
|
0
|
0.00
|
0
|
0
|
0
|
0
|
Nitrate
|
299
|
0
|
0.00
|
0
|
0
|
0
|
0
|
Nitrite
|
310
|
0
|
0.00
|
0
|
0
|
0
|
0
|
Aluminium
|
128
|
0
|
0.00
|
0
|
0
|
0
|
0
|
Iron
|
135
|
0
|
0.00
|
0
|
0
|
0
|
0
|
Manganese
|
119
|
0
|
0.00
|
0
|
0
|
0
|
0
|
Lead
|
357
|
0
|
0.00
|
0
|
0
|
0
|
1
|
PAH
|
104
|
13
|
12.50
|
0
|
6
|
4
|
2
|
Trihalomethanes
|
94
|
0
|
0.00
|
0
|
0
|
0
|
0
|
Total pesticides
|
116
|
0
|
0.00
|
0
|
0
|
0
|
0
|
Other pesticides
|
737
|
0
|
0.00
|
0
|
0
|
0
|
0
|
Alkalinity
|
91
|
0
|
0.00
|
0
|
0
|
0
|
0
|
Antimony
|
40
|
0
|
0.00
|
0
|
0
|
1
|
0
|
Sulphate
|
78
|
0
|
0.00
|
0
|
0
|
0
|
0
|
Surfactants
|
25
|
1
|
4.00
|
0
|
1
|
0
|
0
|
Temperature
|
1,761
|
0
|
0.00
|
0
|
0
|
1
|
0
|
Total Hardness
|
91
|
0
|
0.00
|
0
|
0
|
0
|
0
|
All others
|
2,686
|
0
|
0.00
|
0
|
0
|
0
|
0
|
TOTAL
|
11,435
|
16
|
0.14
|
|
|
|
|
| *23 zones in 2002 and in 2001 |
The new Regulations
In 2003, the Company carried out monitoring for the six new parametric values set down in the new Water
Supply (Water Quality) Regulations 2000. These Regulations came into force on 25 December 2003. The
results are shown in the table below.
|
Parameter
|
Total number
of tests
|
New standard
|
Tests not meeting
the new standard
|
|
Benzene
|
169
|
1.0 µg/l |
0
|
|
Bromate
|
169
|
10.0 µg/l |
0
|
|
1,2 dichloroethane
|
169
|
3.0 µg/l |
0
|
|
Nitrite (exwater treatment works)
|
221
|
0.1 mg/l
|
1
|
|
Clostridium perfringens
|
171
|
0/100 ml
|
0
|
|
Enterococci
|
171
|
0/100 ml
|
0
|
Compliance data for 2003 have also been analysed against the revised standards and the results are
shown in the following table.
|
Parameter
|
Total
number
of tests
|
Current
standard
|
Number of
tests not
meeting current
standard
|
Revised
standard
|
Number of
tests not
meeting revised
standard
|
|
Antimony
|
79
|
10.0 µg/l |
0
|
5.0 µg/l |
5
|
|
Arsenic
|
75
|
50.0 µg/l |
0
|
10.0 µg/l |
0
|
|
Boron
|
96
|
2.0 mg/l
|
0
|
1.0 mg/l
|
0
|
|
Copper
|
93
|
3.0 mg/l
|
0
|
2.0 mg/l
|
0
|
|
Lead
|
357
|
50.0 µg/l |
0
|
25.0 µg/l |
1
|
| |
|
|
|
10.0 µg/l* |
6
|
|
Nickel
|
0
|
50.0 µg/l |
0
|
20.0 µg/l |
0
|
|
Nitrite (at consumers’ taps) |
306
|
0.1 mg/l
|
0
|
0.5 mg/l
|
0
|
|
PAH
|
104
|
0.2 µg/l |
13
|
0.1 µg/l |
0
|
|
Tetrachloroethene Trichloroethene
|
93
93
|
10.0 µg/l 30.0 µg/l |
0 0
|
} 10.0 µg/l |
0
|
| * Final standard not applicable until 2013 |
During 2003, the Company had a programme of work in place to meet the revised standard for lead.
Details of the new and revised standards can be found in chapter J ‘New Regulations and Associated
Programmes of Work’.
Audit and inspection
The Company was inspected or audited by the Inspectorate or its appointed consultants on a number of
occasions during 2003. Where relevant, report summaries are available in the ‘Business and Technical’
section of the Inspectorate’s website under ‘Audit and Inspection’. Details of the subject areas audited or
inspected are given in the following paragraphs:
Audit of regulatory Cryptosporidium monitoring sites
The monitoring equipment at all regulatory sites visited during the year was found to be satisfactory.
Inspection of laboratory analysing for Cryptosporidium
The announced audit on the Analytical Contractor’s
Cryptosporidium
laboratory identified ten regulatory
breaches as well as a number of other minor deficiencies associated with the Standard Operating Protocol.
The Analytical Contractor has undertaken remedial action to rectify the deficiencies identified.
Audit of progress with water treatment works improvement programmes
A desktop audit of four schemes associated with improvement programmes at water treatment works was
carried out together with one site visit. These schemes were for
Cryptosporidium at Fishbourne, Soberton,
Maindell and Lovedean treatment works. Progress with all four schemes was found to be satisfactory.
Audit trails of selected microbiological test results
Vertical audits were carried out on two test results selected at random for the period January 2003 to
March 2003. The Company is being required to take action on deficiencies identified with the audit trail,
laboratory practices and data.
Audit trails of selected nonmicrobiological test results
Vertical audits were carried out on four test results selected at random for the period October 2002 to April
2003. The Company is being required to take action on deficiencies identified with the construction of the
AQC control chart for one parameter; the chain of custody between sampling and delivery to its contract
laboratory for one sample; and for analytical deficiencies identified in respect of its contract laboratory in
the timeliness of the analysis of one sample.
Inspection of one water treatment works and two service reservoirs
Inspections were carried out at Westergate water treatment works and Norehill and Slindon service
reservoir sites. The operation and management of the treatment works/service reservoirs were satisfactory.
However, the Company is being required to take action on a number of minor deficiencies associated with
procedures and disinfection identified at Westergate works; the compliance point at Slindon service
reservoir; site issues and investigation on failures at Slindon and Norehill service reservoirs.
Audit of sampling arrangements
Audits carried out on general sampling arrangements and on one sample round were satisfactory.
A
number of deficiencies were identified with the sample bottles and sampling lines.
Audit of plumbosolvency treatment and control programmes
Progress with the programme of work for plumbosolvency treatment and control measures for lead was
found to be satisfactory.
Incidents
The Inspectorate regarded none of the events notified during 2003 as incidents.
Enforcement action
The table below indicates areas where, in 2003, the Inspectorate considered taking enforcement action for
regulatory breaches, and where an undertaking was submitted or where the Company took appropriate
action.
| Parameter/Area |
Regulation breached |
Location |
Outcome |
| Nickel |
Regulation 13(1) |
All Water Supply Zones |
Assurances given |
Improvement programmes
Water treatment works/service reservoirs
One statement of intent to reduce the risk of Cryptosporidium breaching the treatment standard was due
for completion during 2003. The programme at Farlington treatment works was completed on schedule.
No other improvement programmes associated with treatment works and service reservoirs were due for
completion during 2003.
Lead
The Company’s Regulation 41 programme of work to meet the revised standard for lead set down in the
new Water Supply (Water Quality) Regulations 2000 has been progressing satisfactorily. Plumbosolvency
treatment measures were installed at all sites specified in the programme by 25 December 2003.