To be wholesome, water must comply with the water quality standards for the parameters set out in the
Water Supply (Water Quality) Regulations 1989. In 2003, the Company carried out a total of 152,418 tests
on samples of water leaving its 91 water treatment works, from its 528 service reservoirs and from
consumers’ taps in its 160 water supply zones. Of these, 99.85% (152,191) complied with the standards
set down in the Regulations. However, 0.15% (227) did not meet the standards. A list of the parameters,
the relevant standards and their significance can be found at the beginning of this section.
Water quality leaving treatment works
A comparison of the Company’s performance in 2003 with data for 2002 and 2001, is given below.
Differences over the last three years in the number of treatment works, and in the number of tests carried
out on samples from treatment works, in which coliforms or faecal coliforms were detected, were not
considered significant.
During 2003, failures of the total coliform standard at three works were considered trivial, or unlikely
to recur.
There were no failures of the faecal coliform standard at any of the 91 works.
In 2003, 6,200 regulatory samples for Cryptosporidium were taken at 22 sites. Very low numbers of
oocysts were detected in 104 samples from 12 sites. All results were well below the treatment standard
and there were no reported outbreaks of cryptosporidiosis.
Water quality in service reservoirs
A comparison of the Company’s performance in 2003 with data for 2002 and 2001, is given below.
There
has been a significant decrease since 2001 in the number of service reservoirs, and in the number of
tests carried out on samples from service reservoirs, in which coliforms or faecal coliforms were detected.
All other differences were not considered significant.
Total coliforms were occasionally detected at a number of service reservoirs. However, only one service
reservoir, Cilan SR, failed the total coliform standard. This failure was considered unlikely to recur as Cilan
SR has now been permanently removed from supply.
The single failure of the faecal coliform standard at one service reservoir, Carmel SR, was considered
unlikely to recur as the service reservoir has now been permanently removed from supply.
Water quality in water supply zones
The table below shows the data for the key parameters and any other parameters where there was a failure
of the standard. All other parameters were fully compliant. A comparison is also given for parameters failing
the standards in 2002 and 2001.
|
Parameter
|
Total number
of tests |
Tests not
meeting
standard |
Number of
failures covered
by Undertakings |
Number of zones
not complying with
the standards
(number of zones
in 2003 = 160)* |
|
|
|
No
|
%
|
|
2003
|
2002
|
2001
|
|
Coliforms
|
8,675
|
29
|
0.33
|
0
|
1
|
0
|
0
|
|
Faecal coliforms
|
8,673
|
0
|
0.00
|
0
|
0
|
3
|
3
|
|
Colour
|
754
|
0
|
0.00
|
0
|
0
|
0
|
0
|
|
Turbidity
|
1,951
|
2
|
0.10
|
2
|
2
|
2
|
3
|
|
Odour
|
991
|
3
|
0.30
|
0
|
3
|
2
|
3
|
|
Taste
|
847
|
0
|
0.00
|
0
|
0
|
1
|
0
|
|
Hydrogen ion
|
1,219
|
2
|
0.16
|
0
|
2
|
1
|
3
|
|
Nitrate
|
1,770
|
0
|
0.00
|
0
|
0
|
0
|
0
|
|
Nitrite
|
1,774
|
49
|
2.76
|
0
|
7
|
7
|
26
|
|
Aluminium
|
1,273
|
2
|
0.16
|
1
|
2
|
0
|
3
|
|
Iron
|
3,730
|
34
|
0.91
|
34
|
24
|
31
|
40
|
|
Manganese
|
1,706
|
9
|
0.53
|
2
|
5
|
2
|
7
|
|
Lead
|
825
|
1
|
0.12
|
0
|
1
|
3
|
10
|
|
PAH
|
869
|
57
|
6.56
|
0
|
29
|
18
|
21
|
|
Trihalomethanes
|
523
|
0
|
0.00
|
0
|
0
|
0
|
9
|
|
Total pesticides
|
518
|
0
|
0.00
|
0
|
0
|
1
|
0
|
|
Atrazine
|
531
|
0
|
0.00
|
0
|
0
|
0
|
2
|
|
Isoproturon
|
273
|
0
|
0.00
|
0
|
0
|
0
|
3
|
|
Mecoprop
|
419
|
0
|
0.00
|
0
|
0
|
1
|
1
|
|
Other pesticides
|
16,947
|
0
|
0.00
|
0
|
0
|
0
|
0
|
|
Benzo 3.4 Pyrene
|
869
|
4
|
0.46
|
0
|
1
|
1
|
1
|
|
Oxidizability
|
201
|
0
|
0.00
|
0
|
0
|
1
|
0
|
|
All others
|
19,912
|
0
|
0.00
|
0
|
0
|
0
|
0
|
|
TOTAL
|
75,250
|
192
|
0.26
|
|
|
|
|
| *171 zone in 2002 and 177 zones in 2001 |
The fifth column indicates the number of failures in zones already covered by legally binding undertakings
given by the Company. These undertakings require remedial work to be carried out to ensure compliance
with the individual standard.
During 2003, there was a significant increase in the number of failures for PAH when compared to 2002.
However, the standards for this parameter have been revised, and as the second table below
demonstrates, all tests for this parameter met the revised standard in force from 1 January 2004.
The new Regulations
In 2003, the Company carried out monitoring for the six new parametric values set down in the new Water
Supply (Water Quality) Regulations 2000**. These Regulations came into force on 25 December 2003. The
results are shown in the table below.
|
Parameter
|
Total Number
|
New standard
|
Tests not meeting
|
|
|
of tests
|
|
the new standard
|
|
Benzene
|
674
|
1.0 µg/l |
0
|
|
Bromate
|
654
|
10.0 µg/l |
0
|
|
1,2 dichloroethane
|
665
|
3.0 µg/l |
0
|
|
Nitrite (exwater treatment works)
|
236
|
0.1 mg/l
|
0
|
|
Clostridium perfringens
|
615
|
0/100 ml
|
1
|
|
Enterococci
|
626
|
0/100 ml
|
0
|
Compliance data for 2003 have also been analysed against the revised standards and the results are
shown in the following table.
|
Parameter
|
Total number
of tests |
Current Standard |
Number of tests
not meeting
current standard |
Revised Standard |
Number of tests
not meeting
revised standard
|
|
Antimony
|
179
|
10.0 µg/l |
0
|
5.0 µg/l |
0
|
|
Arsenic
|
177
|
50.0 µg/l |
0
|
10.0 µg/l |
0
|
|
Boron
|
172
|
2.0 mg/l
|
0
|
1.0 mg/l
|
0
|
|
Copper
|
177
|
3.0 mg/l
|
0
|
2.0 mg/l
|
0
|
|
Lead
|
825
|
50.0 µg/l |
1
|
25.0 µg/l |
1
|
|
|
|
|
|
10.0 µg/l * |
7
|
|
Nickel
|
177
|
50.0 µg/l |
0
|
20.0 µg/l |
0
|
| Nitrite (at consumers’ taps) |
1,774 |
0.1 mg/l |
49 |
0.5 mg/l |
0 |
|
PAH
|
869
|
0.2 µg/l |
57
|
0.1 µg/l |
0
|
|
Tetrachloroethene
Trichloroethene |
372
372
|
10.0 µg/l 30.0 µg/l |
0
0 |
} 10.0 µg/l |
0
|
|
* Final standard not applicable until 2013
|
During 2003, the Company had in place programmes of work to meet the new and revised standards.
Details of the new and revised standards can be found in chapter J ‘New Regulations and Associated
Programmes of Work’.
** The Water Supply (Water Quality) Regulations 2001 in Wales
Audit and inspection
The Company was inspected or audited by the Inspectorate or its appointed consultants on a number of
occasions during 2003. Where relevant, report summaries are available in the ‘Business and Technical’
section of the Inspectorate’s website under ‘Audit and Inspection’. Details of the subject areas audited or
inspected are given in the following paragraphs:
Follow up of recommendations made during the 2002 inspections or in connection with water quality incidents
Steps have been taken to implement all of the recommendations arising from the 2002 audit and inspection
process and from assessments of water quality incidents.
Audit of regulatory Cryptosporidium monitoring sites
The monitoring equipment at all regulatory sites visited during the year was found to be satisfactory.
Inspection of laboratory analysing for Cryptosporidium
An unannounced audit on the Company’s Cryptosporidium laboratory was satisfactory.
The announced audit on the Company’s Cryptosporidium laboratory identified four regulatory breaches as
well as a number of other minor deficiencies associated with the approved method set down in the
Standard Operating Protocol Part 2. The Company’s laboratory has taken the required remedial action to
rectify the deficiencies identified.
Audit of membrane treatment plants and membrane integrity testing system
An audit of the six membrane treatment sites and the system of membrane integrity testing was found to
be satisfactory.
Audit of progress with water treatment works improvement programmes
A desktop audit of four schemes associated with improvement programmes at water treatment works
was
carried out together with one site visit. The schemes were for THM at Rhiwgoch treatment works; for
pesticides at Broomy Hill treatment works; for solvents at Midsummer Meadow treatment works; and for
pH at Bontgoch treatment works. Progress with all these schemes was considered satisfactory.
Review of distribution system undertaking
Progress with the programme of mains renovation set out in the Company’s continuing distribution system
undertaking was found to be generally satisfactory. However, the Company is being required to take action
on five minor deficiencies.
Audit of response to selected consumer complaints
A desktop audit of the Company’s response to 12 consumer complaints about drinking water quality was
found to be satisfactory.
Audit trails of selected microbiological test results
Vertical audits were carried out on two test results selected at random for the period March 2003 to May
2003. There were no significant deficiencies.
Audit trails of selected nonmicrobiological test results
Vertical audits were carried out on eight test results selected at random for the period June 2002 to March
2003. The Company is being required to take action on deficiencies identified with scheduling of samples
at regular intervals. Deficiencies were also identified in the arrangements for reviewing control charts for
many of the earlier samples but the Inspectorate accepts that Company’s contract laboratory has since
introduced new procedures for such reviews. These will be followed up by the Inspectorate in the
next audit.
Inspection of one water treatment works and two service reservoirs
Inspections were carried out at Felindre water treatment works and Beddgelert and Rhosgadfan service
reservoir sites. The operation and management of the treatment works and service reservoirs were
satisfactory. However, the Company is being required to take action on a couple of minor deficiencies
associated with calibration of equipment identified at Felindre WTW, and the protocol for the
decommissioning of service reservoirs.
Audit of work on distribution system
An inspection was carried out on a major mains laying and replacement project at Ystradgynlais. The
operation and management of the project weres satisfactory. The Company is being required to take action
on one minor deficiency identified during the inspection regarding the hypochlorite solution used onsite for
sterilisation of equipment and mains.
Audit of plumbosolvency treatment and control programmes
Progress with the programme of work for plumbosolvency treatment and control measures for lead was
found to be generally satisfactory. However, the Company is being required to take action regarding
consistency of phosphate dosing at one works, and on its procedures for bringing standby supplies back
into supply.
Assessment of procedures for working on under pressure systems
A desktop assessment of the Company’s protocols and procedures for the drilling and tapping of under
pressure mains systems was carried out. The procedures and systems in place were satisfactory.
Audit of one analytical laboratory
An audit of one of the Company’s analytical contract laboratories was carried out. The audit identified a
number of deficiencies regarding traceability, calibration and analytical quality control within the laboratory.
The laboratory was required to take action on these deficiencies, and a followup inspection carried out
later in 2003 confirmed that corrective action had been taken on a number of issues. The laboratory will be
subject to further audit during 2004.
Incidents
The Inspectorate regarded 11 events notified during 2003 as incidents. Further details of these incidents
are given in the table below.
Eight of the incidents were fully investigated and assessed by the Inspectorate during 2003. Each was of
relatively short duration and, where applicable, the Company took appropriate action to protect public
health. The Company is being required to take action on a number of deficiencies identified in respect of
carrying out risk assessments, internal communications, site supervision and training, notifying consumers
and sampling. The three remaining incidents were still under consideration at the end of 2003.
During 2003, investigations were also completed for four incidents that occurred in 2002.
For one of these incidents involving discolouration of water supplies to potentially 13,000 consumers in the
Cray district of Swansea following planned maintenance work on the distribution system, the Company
admitted that it supplied water unfit for human consumption during the incident, contrary to Section 70 of
the Water Industry Act 1991, and received a formal caution.
Enforcement action
The table below indicates areas where, in 2003, the Inspectorate considered taking enforcement action for
regulatory breaches, and where an undertaking was submitted or where the Company took appropriate
action.
| Parameter/Area |
Regulation breached |
Location |
Outcome |
Benzo 3,4-pyrene |
3(3)(d) |
Pontllanfraith |
Undertaking pending |
The Inspectorate was minded to initiate Enforcement action for submission of an erroneous and inadequate
data return for 2003, particularly as a similar problem occurred for 2002 data. However, the Company has
given assurances that the information management system recently installed will resolve the issue.
Enforcement action will be taken if further deficiencies with provision of information occur.
Improvement programmes
Water treatment works/service reservoirs
One undertaking associated with treatment works was due for completion during 2003. This was to install
treatment at Broomy Hill treatment works to remove pesticides. The undertaking was completed on
schedule.
One Regulation 41 programme of work to meet the new and revised standards set down in the new Water
Supply (Water Quality) Regulations 2000* was due for completion in 2003. This was to remove the risk of
solvents occurring in the supply from Midsummer Meadow treatment works. The programme was
completed on schedule.
No other improvement programmes at treatment works and service reservoirs were due for completion
during 2003.
Distribution
Progress with the continuing distribution system undertaking was satisfactory. During 2003, 586 kilometres
of mains were renovated. The Company is required to renovate a further 3134 kilometres of mains by
31 March 2010.
Lead
The Company’s Regulation 41 programme of work to meet the revised standard for lead set down in the
new Water Supply (Water Quality) Regulations 2000 has been progressing satisfactorily. Plumbosolvency
treatment measures were installed at all sites specified in the programme by 25 December 2003.
*The Water Supply (Water Quality) Regulations 2001 in Wales