14 Severn Trent Water Limited
|
Overall water quality supplied by Severn Trent Water Limited in 2003: |
- 280,462 tests were carried out on samples taken by Severn Trent Water Limited in 2003.
- 99.93% of these tests complied with the Regulations.
|
|
Company Information |
|
Amount of Water Supplied: |
1,958 Ml/d |
|
Consumers Supplied: |
7.27 million |
|
Areas of Supply: |
Stretches from the Humber |
| |
Estuary in the north to the Bristol |
| |
Channel in the south, and from |
| |
Llyn Clywedog, Wales in the |
| |
west to Lincolnshire in the east. |
|
Water Composition: |
65% from rivers and reservoirs |
| |
35% from boreholes and aquifers |
|
Treatment Works: |
161 |
|
Service Reservoirs: |
626 |
|
Km of Mains: |
45,676 |
|
Water Supply Zones: |
284 |
|
|
Water quality at treatment works, in service reservoirs and in water supply zones
To be wholesome, water must comply with the water quality standards for the parameters set out in the
Water Supply (Water Quality) Regulations 1989. In 2003, the Company carried out a total of 280,462 tests
on samples of water leaving its 161 water treatment works, from its 626 service reservoirs and from
consumers’ taps in its 284 water supply zones. Of these, 99.93% (280,277 ) complied with the standards
set down in the Regulations. However, 0.07% (185) tests did not meet the standards. A list of the
parameters, the relevant standards and their significance can be found at the beginning of this section.
Water quality leaving treatment works
A comparison of the Company’s performance in 2003 with data for 2002 and 2001, is given below.
Differences over the last three years in the number of treatment works, and in the number of tests carried
out on samples from treatment works, in which coliforms or faecal coliforms were detected, were not
considered significant.
During 2003, the failures of the total coliform standard at ten works were considered trivial or unlikely to recur. Single failures of the faecal coliform standard occurred at two works. These were regarded as trivial or unlikely to recur.
In 2003, 3,043 regulatory samples for Cryptosporidium were taken at nine sites. Very low numbers of
oocysts were detected in eight samples from five sites. All results were well below the treatment standard
and there were no reported outbreaks of cryptosporidiosis.
Water quality in service reservoirs
A comparison of the Company’s performance in 2003 with data for 2002 and 2001, is given below.
Differences over the last three years in the number of service reservoirs, and in the number of tests carried
out on samples from service reservoirs, in which coliforms or faecal coliforms were detected, were not
considered significant.
During 2003, total coliforms were occasionally detected at a number of service reservoirs. However, there
were no failures of the total coliform standard at any service reservoir.
Single failures of the faecal coliform standard at three service reservoirs were considered trivial or unlikely
to recur.
Water quality in water supply zones
The table below shows the data for the key parameters and any other parameters where there was a failure
of the standard. All other parameters were fully compliant. A comparison is also given for parameters failing
the standards in 2002 and 2001.
|
Parameter
|
Total number
of tests |
Tests not
meeting
standard |
Number of
failures
covered by
Undertakings |
Number of zones not
complying with the standards
(number of zones in
2003 = 284)* |
|
|
|
No
|
%
|
|
2003
|
2002
|
2001
|
|
Coliforms
|
19,194
|
74
|
0.39
|
11
|
0
|
0
|
0
|
|
Faecal coliforms
|
19,194
|
5
|
0.03
|
0
|
5
|
5
|
5
|
|
Colour
|
1,434
|
0
|
0.00
|
0
|
0
|
0
|
0
|
|
Turbidity
|
4,631
|
1
|
0.02
|
0
|
1
|
0
|
0
|
|
Odour
|
1,342
|
1
|
0.07
|
0
|
1
|
0
|
0
|
|
Taste
|
1,427
|
1
|
0.07
|
0
|
1
|
0
|
0
|
|
Hydrogen ion
|
1,689
|
1
|
0.06
|
0
|
1
|
0
|
0
|
|
Nitrate
|
5,899
|
1
|
0.02
|
0
|
1
|
1
|
1
|
|
Nitrite
|
2,455
|
6
|
0.24
|
0
|
3
|
3
|
2
|
|
Aluminium
|
1,744
|
1
|
0.06
|
0
|
1
|
1
|
3
|
|
Iron
|
5,822
|
25
|
0.43
|
10
|
18
|
25
|
23
|
|
Manganese
|
1,797
|
2
|
0.11
|
0
|
2
|
3
|
1
|
|
Lead
|
736
|
1
|
0.14
|
0
|
1
|
4
|
3
|
|
PAH
|
1,133
|
29
|
2.56
|
0
|
17
|
21
|
20
|
|
Trihalomethanes
|
810
|
0
|
0.00
|
0
|
0
|
0
|
0
|
|
Total pesticides
|
1,503
|
0
|
0.00
|
0
|
0
|
0
|
0
|
|
Atrazine
|
1,712
|
1
|
0.06
|
0
|
1
|
0
|
0
|
|
Other pesticides
|
51,207
|
0
|
0.00
|
0
|
0
|
0
|
0
|
|
Sulphate
|
688
|
0
|
0.00
|
0
|
0
|
0
|
1
|
|
All others
|
59,962
|
0
|
0.00
|
0
|
0
|
0
|
0
|
|
TOTAL
|
184,379
|
149
|
0.08
|
|
|
|
|
| *285 zones in 2002 and in 2001 |
The fifth column indicates the number of failures in zones already covered by legally binding undertakings
given by the Company. These undertakings require remedial work to be carried out to ensure compliance
with the individual standard.
The new Regulations
In 2003, the Company carried out monitoring for the six new parametric values set down in the new Water
Supply (Water Quality) Regulations 2000. These Regulations came into force on 25 December 2003. The
results are shown in the table below.
|
Parameter
|
Total number
of tests
|
New standard
|
Tests not meeting
the new standard
|
|
|
|
Benzene
|
645
|
1.0 µg/l |
0
|
|
Bromate
|
410
|
10.0 µg/l |
0
|
|
1,2 dichloroethane
|
645
|
3.0 µg/l |
0
|
|
Nitrite (exwater treatment works)
|
645
|
0.1 mg/l
|
0
|
|
Clostridium perfringens
|
296
|
0/100 ml
|
0
|
|
Enterococci
|
1,075
|
0/100 ml
|
1
|
Compliance data for 2003 have also been analysed against the revised standards and the results are
shown in the following table.
Parameter |
Total
number
of tests |
Current
standard |
Number of
tests not
meeting current
standard |
Revised
standard |
Number of
tests not
meeting revised
standard |
Antimony |
252 |
10.0 µg/l |
0 |
5.0 µg/l |
0 |
Arsenic |
252 |
50.0 µg/l |
0 |
10.0 µg/l |
0 |
Boron |
252 |
2.0 mg/l |
0 |
1.0 mg/l |
0 |
Copper |
292 |
3.0 mg/l |
0 |
2.0 mg/l |
0 |
Lead |
736 |
50.0 µg/l |
1 |
25.0 µg/l |
5 |
|
|
|
|
10.0 µg/l* |
38 |
Nickel |
252 |
50.0 µg/l |
0 |
20.0 µg/l |
0 |
Nitrite (at consumers’ taps) |
2,456 |
0.1 mg/l |
6 |
0.5 mg/l |
0 |
PAH |
1,133 |
0.2 µg/l |
29 |
0.1 µg/l |
0 |
Tetrachloroethene Trichloroethene |
633
633 |
10.0 µg/l 30.0 µg/l |
0
0 |
} 10.0 µg/l |
0 |
| * Final standard not applicable until 2013 |
During 2003, the Company had in place a number of programmes of work to meet the new and revised standards.
Details of the new and revised standards can be found in chapter J ‘New Regulations and Associated
Programmes of Work’.
Audit and inspection
The Company was inspected or audited by the Inspectorate or its appointed consultants on a number of
occasions during 2003. Where relevant, report summaries are available in the ‘Business and Technical’
section of the Inspectorate’s website under ‘Audit and Inspection’. Details of the subject areas audited or
inspected are given in the following paragraphs:
Follow up of recommendations made during the 2002 inspections or in connection with water quality incidents
Steps have been taken to implement the vast majority of the recommendations arising from the 2002 audit
and inspection process and from assessments of water quality incidents. Further action is to be taken in
respect of one recommendation regarding the correct nomenclature on the public record.
Audit of regulatory Cryptosporidium monitoring sites
The monitoring equipment at all regulatory sites visited during the year was found to be satisfactory.
Inspection of laboratory analysing for Cryptosporidium
An unannounced audit on the Company’s Cryptosporidium laboratory was satisfactory.
The announced audit on the Company’s Cryptosporidium laboratory identified four regulatory breaches as
well as a number of other minor deficiencies associated with the approved method set down in the
Standard Operating Protocol Part 2. The Company has taken the required remedial action to rectify the
deficiencies identified.
Audit of progress with water treatment works improvement programmes
Six schemes were selected for detailed audit and one site visit was carried out. The schemes audited were
for nitrate at Oakley Farm treatment works; for arsenic at Astley, Lee Brockhurst and Preston Brockhurst
treatment works; for chlorinated solvents at Whitley treatment works; and for
Cryptosporidium at Llandinam
treatment works. Progress with the schemes was generally satisfactory; however, the Company is required
to take action on one issue associated with the scheme at Whitely. Additionally, there are outstanding
issues associated with the Oakley Farm scheme which are the subject of further discussions with the
Inspectorate.
Review of distribution system undertaking
Progress with the programme of mains renovation set out in the Company’s continuing distribution system
undertaking was found to be generally satisfactory.
Audit trails of selected microbiological test results
Vertical audits were carried out on two test results selected at random for the period February 2002 to
February 2003. The Company is being required to take action on deficiencies identified with analytical
quality control.
Audit trails of selected nonmicrobiological test results
Vertical audits were carried out on 13 test results selected at random for the period May 2002 to April
2003. The Company is being required to take action on deficiencies identified with the method of analysis
and calibration in respect of one parameter; and the construction of control charts in respect of one
parameter. Deficiencies were also identified in the arrangements for reviewing control charts for many of
the
earlier samples but the Inspectorate accepts that Company’s laboratory has since introduced new
procedures for such reviews. These will be followed up by the Inspectorate in the next audit.
Inspection of one water treatment works and two service reservoirs
Inspections were carried out at Whitacre water treatment works and at Corley and Meriden service
reservoir sites. The general operation and management of the sites were satisfactory. However, the
Company is being required to take action on a number of minor deficiencies identified at Whitacre WTW
associated with the compliance sampling point; documentation regarding process diagrams and
authorisations; and calibration of equipment; and in addition, deficiencies were noted at Meriden SR
regarding randomisation of sampling and response to unsatisfactory results.
Audit of plumbosolvency treatment and control programmes
Progress with the programme of work for plumbosolvency treatment and control measures for lead was
found to be satisfactory.
Incidents
The Inspectorate regarded six events notified during 2003 as incidents. Further details of these incidents
are given in the table below.
All of the incidents were fully investigated and assessed by the Inspectorate during 2003. Each was of
relatively short duration and, where applicable, the Company took appropriate action to protect public
health.
During 2003, investigation was also completed for one incident that occurred in 2002.
Nature of incident Assessment completed during 2003
Enforcement action
The table below indicates areas where, in 2003, the Inspectorate considered taking enforcement action
for
regulatory breaches, and where an undertaking was submitted or where the Company took appropriate
action.
|
Parameter/Area
|
Regulation breached
|
Location
|
Outcome
|
|
Iron
|
Regulation 3(3)(c)
|
Sinfin, Chellaston &
Shardlow water supply
zone;
Michelover, Mackworth, Hatton & Sudbury water supply zone;
Duffield, Holbrook & Idringhay water supply zone
|
Undertaking agreed
|
Improvement programmes
Water treatment works/service reservoirs
Twentytwo Regulation 41 programmes of work to meet the new and revised standards set down in the
new Water Supply (Water Quality) Regulations 2000 were due for completion in 2003. These were to install
treatment at 18 treatment works to remove arsenic; at two treatment works to remove THM; at two
treatment works to remove bromate; and at one treatment works to remove solvents. The programmes
were completed on schedule.
Eight statements of intent to reduce the risk of Cryptosporidium breaching the treatment standard were
due for completion during 2003. Seven of the programmes were completed on or ahead of schedule.
The
remaining programme has been delayed due to land access issues which are beyond the control of
the Company.
One statement of intent for meeting the iron and manganese standard was due for completion during 2003.
The programme was completed on schedule.
No other programmes of work associated with treatment works or service reservoirs were due for
completion during 2003.
Distribution
Progress with the continuing distribution system undertaking was generally satisfactory. During 2003, 502
km of mains were renovated. The Company is required to renovate a further 247 km of mains by 31 March
2005.
Lead
The Company’s Regulation 41 programme of work to meet the revised standard for lead set down in the
new Water Supply (Water Quality) Regulations 2000 has been progressing satisfactorily. Plumbosolvency
treatment measures were installed at all sites specified in the programme by 25 December 2003.